Software project effort estimation assistant. Outputs three-point estimates (optimistic/most-likely/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns.
Trending
Steady talk.thin dataabout the whole repository
Who's talking about zebbern/claude-code-guide
- @tom-doerr.bsky.social“https://github.com/zebbern/claude-code-guide”Bluesky · Jun 10, 2026 · 2 likes
- A Hacker News story“Claude Code Guide”Hacker News · Jul 1, 2025 · 2 points
- @tom-doerr.bsky.social“https://github.com/zebbern/claude-code-guide”Bluesky · Apr 4, 2026 · 1 likes
- coderPerseus/blog“使用两个月的 Claude Code ,总结下我的最佳实践”GitHub · Jul 20, 2025 · 1 reactions
- sudosubin/agents.nix“agent-skills.github.zebbern.claude-code-guide: init at 0-unstable-2026-05-31”GitHub · Oct 3, 2026
The biggest 5 of 8 mentions linking to the repository that our crawl found. Each line is their own headline.
See all 8
Talked about on GitHub, Bluesky and Hacker News (8 times).
On GitHub · 5
- Jul 20, 2025使用两个月的 Claude Code ,总结下我的最佳实践 — coderPerseus/blog1 reaction · 1 comment
- Oct 3, 2026agent-skills.github.zebbern.claude-code-guide: init at 0-unstable-2026-05-31 — sudosubin/agents.nix0 reactions
- Apr 13, 2026Audit candidate: zebbern/claude-code-guide — xiaolai/nlpm0 reactions · 3 comments
- Apr 6, 2026Audit candidate: zebbern/claude-code-guide — xiaolai/nlpm0 reactions · 1 comment
- Nov 23, 2025AI 相关调研 — wenxueliu/cognitive_center0 reactions · 5 comments
On Bluesky · 2
- Jun 10, 2026https://github.com/zebbern/claude-code-guide — @tom-doerr.bsky.social2 likes and reposts
- Apr 4, 2026https://github.com/zebbern/claude-code-guide — @tom-doerr.bsky.social1 likes and repost
On Hacker News · 1
- Jul 1, 2025Claude Code Guide2 points
In this repository80 other files it gives its agents.
- skills/composition-patterns/AGENTS.mdAGENTS.md
- skills/react-best-practices/AGENTS.mdAGENTS.md
- academic-paper-reviewerSkill
- active-directory-attacksSkill
- api-fuzzing-bug-bountySkill
- api-shape-explorerSkill
- audit-flowSkill
- authentication-patternsSkill
- aws-penetration-testingSkill
- broken-authenticationSkill
- burp-suite-testingSkill
- cachingSkill
- chart-imageSkill
- cloud-penetration-testingSkill
- code-documenterSkill
- code-to-diagramSkill
- code-vuln-auditSkill
- vercel-composition-patternsSkill
- cross-examineSkill
- cv-tailorSkill
- database-optimizerSkill
- database-scoutSkill
- dataset-quality-auditSkill
- data-viz-rendererSkill
- deep-module-refactorSkill
- design-system-builderSkill
- dev-guide-generatorSkill
- ethical-hacking-methodologySkill
- file-path-traversalSkill
- html-injection-testingSkill
- http-load-profilerSkill
- idor-testingSkill
- linux-privilege-escalationSkill
- linux-shell-scriptingSkill
- localization-toolkitSkill
- log-error-digestSkill
- metasploit-frameworkSkill
- network-101Skill
- nextjs-developerSkill
- pdfSkill
- pentest-checklistSkill
- pentest-commandsSkill
- pipeline-blueprintSkill
- playwright-ciSkill
- playwright-coreSkill
- playwright-migrationSkill
- playwright-cliSkill
- playwright-pomSkill
- playwright-skillSkill
- privilege-escalation-methodsSkill
- r2-uploadSkill
- r3f-animationSkill
- r3f-best-practicesSkill
- vercel-react-best-practicesSkill
- red-team-toolsSkill
- regression-modelerSkill
- regulatory-audit-generatorSkill
- repo-auditSkill
- route-to-openapiSkill
- scanning-toolsSkill
- The first 60 shown.
The file
We split this skill into the rules it gives an agent
6 rules. About 0 are common, 6 are distinctive, and 0 are very specific to this project.
≈0
Common · estimate
Many files like this have a rule of this kind.
≈6
Distinctive · estimate
This author's own choices. Worth a look.
0
Very specific
Tied to their project's names, files or tools. Probably skip.
- Common
- Distinctive
- Very specific
- Distinctive: line 74
If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
- Distinctive: line 94
When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:
- Distinctive: line 109
Discuss discrepancies: When estimates differ by more than 2 sizes, a discussion is mandatory
- Distinctive: line 165
After calculating Unadjusted Function Points (UFP):
- Distinctive: line 196
After completing the estimation, verify that the following factors have been accounted for:
- Distinctive: line 229
After the Agent completes the estimation, it should produce output in the following format:
≈ “Common” is an estimate: at least 1 in 5 of the 213,895 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.
Files
Project Sizing Guide — Software Project Effort Estimation
Helps teams produce scientifically grounded effort estimates for software projects, based on three major methodologies: Three-Point Estimation (PERT), T-shirt Sizing, and Function Point Analysis (FPA). Outputs optimistic, most-likely, and pessimistic values along with risk intervals.
Quick Start
- User provides a requirements description → Agent identifies functional modules and breaks them into a Work Breakdown Structure (WBS)
- Select an estimation method → Choose the best-fit approach based on project stage and available information
- Estimate each item → Assign O/M/P (Optimistic / Most Likely / Pessimistic) values to every work package
- Aggregate and report → Generate an estimation report with risk analysis and confidence intervals
A calculation helper is available:
python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'Method Selection Guide
| Scenario | Recommended Method | Rationale |
| Early feasibility study, rough budgeting | T-shirt Sizing | Little information available; quickly align on order of magnitude |
| Sprint planning, iteration estimation | Three-Point Estimation (PERT) | Good granularity with confidence intervals |
| Contract bidding, large-project RFPs | Function Point Analysis (FPA) | Most rigorous; industry-comparable |
| Team has historical data | PERT + historical calibration | Combines empirical correction with data |
Method 1: Three-Point Estimation (PERT)
Core Formulas
| Metric | Formula | Meaning |
| Expected Value E | (O + 4M + P) / 6 | Weighted average effort |
| Standard Deviation σ | (P − O) / 6 | Estimation uncertainty |
| Variance V | σ² | Used to aggregate across tasks |
| Project Total Expected | ΣE | Sum of individual expected values |
| Project Total Std Dev | √(ΣV) | Square root of summed variances |
Where:
- O (Optimistic): Shortest duration assuming everything goes smoothly
- M (Most Likely): Duration under normal circumstances
- P (Pessimistic): Longest duration when significant difficulties arise
Confidence Intervals
| Confidence Level | Interval | Use Case |
| 68.3% | E ± 1σ | Internal rough estimates |
| 90% | E ± 1.645σ | Project planning |
| 95% | E ± 2σ | External quotes |
| 99.7% | E ± 3σ | Contractual commitments |
Steps
- Build the WBS: Decompose requirements into the smallest independently estimable units (recommended ≤ 5 person-days each)
- Three-point estimation: For each work package, provide O / M / P values (use consistent units: person-hours or person-days)
- Calculate per-task expected value and standard deviation
- Aggregate project-level metrics: Total Expected = ΣE, Total Std Dev = √(Σσ²)
- Output confidence intervals: Choose a confidence level based on risk appetite
O/M/P Estimation Rules of Thumb
- O should not be less than 30% of M (overly optimistic suggests essential steps were overlooked)
- P should not exceed 5× M (overly pessimistic suggests unclear requirements that need clarification first)
- If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
- The P/O ratio (spread ratio) reflects uncertainty: < 2 = low risk, 2–4 = medium risk, > 4 = high risk
Method 2: T-shirt Sizing
Size Reference Table
| Size | Typical Range (person-days) | Typical Story Points | Suitable For |
| XS | 0.25 – 0.5 | 1 | Config changes, copy edits, simple bug fixes |
| S | 0.5 – 2 | 2 – 3 | Single-component development, simple API, minor UI tweaks |
| M | 2 – 5 | 5 – 8 | Complete feature module, moderately complex API |
| L | 5 – 15 | 13 – 21 | Cross-module features requiring integration |
| XL | 15 – 40 | 34 – 55 | Subsystem-level development requiring architecture design |
| XXL | 40+ | 89+ | Should be split across multiple iterations; not recommended as a single estimation unit |
Converting T-shirt Sizes to Three-Point Estimates
When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:
| Size | O (person-days) | M (person-days) | P (person-days) |
| XS | 0.25 | 0.5 | 1 |
| S | 0.5 | 1 | 2.5 |
| M | 2 | 3.5 | 7 |
| L | 5 | 10 | 20 |
| XL | 15 | 25 | 50 |
| XXL | 40 | 70 | 150 |
Steps
- Team alignment: Confirm what each size means (the table above is a reference; teams may customize)
- Independent assessment: Each person assigns a size independently to avoid anchoring bias
- Discuss discrepancies: When estimates differ by more than 2 sizes, a discussion is mandatory
- Reach consensus: Adopt the team consensus value
- Convert to numbers (optional): Use the table above to derive O/M/P values
Method 3: Function Point Analysis (FPA)
Five Function Component Types
| Component Type | Abbreviation | Definition | Example |
| Internal Logical File | ILF | Logical data group maintained by the application | Users table, Orders table |
| External Interface File | EIF | Data group referenced but not maintained by the application | Third-party exchange rate data |
| External Input | EI | Data processing entering the system from outside | Form submission, API POST |
| External Output | EO | Data generated and sent outside the system | Report generation, exports |
| External Inquiry | EQ | Simple data retrieval + display | List queries, detail pages |
Complexity Weight Matrix
| Component Type | Low | Medium | High |
| ILF | 7 | 10 | 15 |
| EIF | 5 | 7 | 10 |
| EI | 3 | 4 | 6 |
| EO | 4 | 5 | 7 |
| EQ | 3 | 4 | 6 |
Complexity Assessment Rules
ILF / EIF Complexity (based on DET – Data Element Types and RET – Record Element Types):
| DET 1-19 | DET 20-50 | DET 51+ | |
| RET 1 | Low | Low | Medium |
| RET 2-5 | Low | Medium | High |
| RET 6+ | Medium | High | High |
EI Complexity (based on DET and FTR – File Types Referenced):
| DET 1-4 | DET 5-15 | DET 16+ | |
| FTR 0-1 | Low | Low | Medium |
| FTR 2 | Low | Medium | High |
| FTR 3+ | Medium | High | High |
EO / EQ Complexity (based on DET and FTR):
| DET 1-5 | DET 6-19 | DET 20+ | |
| FTR 0-1 | Low | Low | Medium |
| FTR 2-3 | Low | Medium | High |
| FTR 4+ | Medium | High | High |
Converting Function Points to Effort
After calculating Unadjusted Function Points (UFP):
- Calculate the Value Adjustment Factor (VAF) (optional; deprecated since IFPUG 4.3+ but still used by some teams)
- 14 General System Characteristics (GSC), each scored 0–5
- VAF = 0.65 + 0.01 × Σ(GSC)
- Adjusted Function Points AFP = UFP × VAF
Function points to person-hours
- Industry benchmark: 8–15 person-hours per function point (varies by language and team maturity)
Technology Stack Person-hours / FP Notes Low-code / Mature Frameworks 4 – 8 Many reusable components available Python / JS / Modern Web 8 – 12 Mainstream development productivity Java / C# Enterprise 10 – 15 Includes architecture and standards overhead Embedded / C / C++ 15 – 25 High debugging and testing cost Legacy System Maintenance 20 – 30 Comprehension and regression cost
Steps
- Identify function components: List all ILFs, EIFs, EIs, EOs, and EQs
- Assess complexity: Rate each component as Low / Medium / High
- Calculate UFP: Sum (count × weight) for all components
- Select conversion factor: Choose person-hours per FP based on technology stack
- Compute total effort: UFP × conversion factor
- Add buffer: A 15–30% management and risk buffer is recommended
Estimation Adjustment Factor Checklist
After completing the estimation, verify that the following factors have been accounted for:
Technical Factors
- Technology stack familiarity (Is the team experienced? If unfamiliar, add 30–50%)
- Technical debt (Poor legacy code quality? Add 20–40%)
- Third-party dependencies (Unstable APIs? Missing documentation? Add 10–30%)
- Performance / security requirements (Special non-functional requirements? Add 15–25%)
Team Factors
- Team size (Communication overhead increases significantly above 5 people; add ~5% per person)
- Personnel turnover risk (Key members may leave? Add 15–25%)
- Parallel projects (Team context-switching across multiple projects? Add 20–30%)
- Onboarding new members (New hires? Expect ~50% reduced efficiency for the first 2 weeks)
Process Factors
- Requirements stability (Requirements likely to change? Add 20–50%)
- Approval processes (Multiple layers of approval needed? Add 10–20%)
- Deployment complexity (Multi-environment, multi-region deployments? Add 10–15%)
- Compliance requirements (Audit or compliance processes? Add 15–30%)
Commonly Underestimated Work
- Code review: +10–15%
- Unit test authoring: +15–25%
- Integration / E2E testing: +10–20%
- Documentation: +5–15%
- Bug fixing and regression: +10–20%
- Environment setup and DevOps: +5–10%
- Meetings and communication: +10–15%
Estimation Output Template
After the Agent completes the estimation, it should produce output in the following format:
## Estimation Report: [Project / Feature Name]
### Estimation Method: [PERT / T-shirt / FPA]
### Work Package Breakdown
| # | Work Package | O (person-days) | M (person-days) | P (person-days) | E (person-days) | σ |
|---|-------------|-----------------|-----------------|-----------------|-----------------|---|
| 1 | xxx | x | x | x | x.x | x.x |
| 2 | xxx | x | x | x | x.x | x.x |
### Summary
- Total expected effort: X person-days
- Total standard deviation: X person-days
- 68% confidence interval: X – X person-days
- 90% confidence interval: X – X person-days
- 95% confidence interval: X – X person-days
### Adjustment Factors
- [Factors considered and adjustments applied]
### Final Recommendation
- For internal planning: X person-days (90% confidence)
- For external quotes: X person-days (95% confidence)
### Risk Alerts
- [Key risk items and mitigation suggestions]Calculation Tool
The scripts/estimate_calculator.py script supports numerical calculations for all three estimation methods:
# Three-Point Estimation (PERT)
python3 scripts/estimate_calculator.py --method pert \
--tasks '[{"name":"Login Module","O":2,"M":3,"P":8},{"name":"Payment Module","O":5,"M":10,"P":20}]'
# T-shirt Size Conversion
python3 scripts/estimate_calculator.py --method tshirt \
--tasks '[{"name":"Login Module","size":"M"},{"name":"Payment Module","size":"L"}]'
# Function Point Analysis
python3 scripts/estimate_calculator.py --method fpa \
--components '[{"type":"ILF","complexity":"medium","count":3},{"type":"EI","complexity":"low","count":5}]' \
--hours-per-fp 10References
- IFPUG (International Function Point Users Group) CPM 4.3.1
- PMI PMBOK Guide — 6th Edition, Section 6.4: Estimate Activity Durations
- Steve McConnell, Software Estimation: Demystifying the Black Art
- Mike Cohn, Agile Estimating and Planning
Does it work?
Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.
No reviews yet
People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.
- It worked
- Partly
- It didn't
Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.
Your trail
Files you open will collect here, so you can find them again.
Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.
Now do this for your own.
Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.